DIFC and ADGM procedure guides
When is the deadline for pay the accepted sum under a part 18 offer?
Party liable under an accepted single-sum offer must check ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5). Within fourteen days of acceptance. The identified act is to pay the accepted sum to the claimant. Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step. This guide preserves the source boundary without a calculated final date or paid calculation.
- Period
- Within fourteen days of acceptance
- Trigger
- Actual acceptance
- Rule
- ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)
The maintained official ADGM index links the consolidated Rules and Amendment No. 1 of 2025, reissued October 17, 2025. Current division, Fast Track allocation, practice directions and orders remain material. This guide does not assume a historical matter uses that edition.
Source guide · No automated date
Check the applicable procedure
Source guide. Within fourteen days of acceptance. Establish actual acceptance and the applicable branch. No computed date or paid calculation is available because actual-event and completion qualifications remain unverified.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
When is the deadline for pay the accepted sum under a part 18 offer?
Party liable under an accepted single-sum offer must check ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5). Within fourteen days of acceptance. The identified act is to pay the accepted sum to the claimant. Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step. This guide preserves the source boundary without a calculated final date or paid calculation.
Responsible actor. Party liable under an accepted single-sum offer.
Actual acceptance
Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step.
Source guide. Within fourteen days of acceptance. Establish actual acceptance and the applicable branch. No computed date or paid calculation is available because actual-event and completion qualifications remain unverified.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)How does this provision count time?
- Within fourteen days of acceptance
- ADGM Rule 6 counts days as clear days, excluding the start and an event-defined end. For periods of five days or less, Saturdays, Sundays and public holidays do not count. Actual month periods and operative events need their own source review.
- Current Rule 7(5), as amended on October 17, 2025, concerns a specified act whose period ends on a closed registry day, subject to the relevant practice direction. The amendment removed the old restriction to acts at the registry. Minimum notice, status and agreed caps remain distinct; no automatic final date is shown.
ADGM Rule 6 counts days as clear days, excluding the start and an event-defined end. For periods of five days or less, Saturdays, Sundays and public holidays do not count. Actual month periods and operative events need their own source review.
Current Rule 7(5), as amended on October 17, 2025, concerns a specified act whose period ends on a closed registry day, subject to the relevant practice direction. The amendment removed the old restriction to acts at the registry. Minimum notice, status and agreed caps remain distinct; no automatic final date is shown.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Which facts prevent one automatic date?
Source guide. Within fourteen days of acceptance. Establish actual acceptance and the applicable branch. No computed date or paid calculation is available because actual-event and completion qualifications remain unverified.
Which conditions and exceptions apply?
- Applicable statutory or procedural branch
- Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step.
- Applicable edition and transition
- The maintained official ADGM index links the consolidated Rules and Amendment No. 1 of 2025, reissued October 17, 2025. Current division, Fast Track allocation, practice directions and orders remain material. This guide does not assume a historical matter uses that edition.
- Source guide. Within fourteen days of acceptance. Establish actual acceptance and the applicable branch. No computed date or paid calculation is available because actual-event and completion qualifications remain unverified.
- ADGM Part 18 offer minimum acceptance period concerns specify the acceptance period and required consequences from actual offer terms and actual trial timing, with not less than twenty-one days. ADGM money judgment payment concerns comply with the money judgment or order from actual judgment or order, with within fourteen days. ADGM costs payment after an order or certificate concerns pay the costs amount from actual order stating the amount, or later assessment certificate, with within fourteen days of the applicable instrument. Those events do not replace actual acceptance for this step.
What must the responsible actor complete?
Questions about this procedure
When is the deadline for pay the accepted sum under a part 18 offer?
What period governs ADGM accepted Part 18 offer payment?
Within fourteen days of acceptance. ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5) supplies this period. It does not by itself establish the actual event or a final completion date.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Which event controls ADGM accepted Part 18 offer payment?
Establish actual acceptance. Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step. The catalog date label does not prove this event.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Who completes the step for ADGM accepted Part 18 offer payment?
Party liable under an accepted single-sum offer. The source identifies the act as pay the accepted sum to the claimant. Filing, service, payment, a minimum notice and a stay status must remain distinct.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Which conditions change ADGM accepted Part 18 offer payment?
Written agreement or a Court order can alter the period. Actual required approval affects settlement consequences. Judgment for an unpaid sum is a separate optional step. The maintained official ADGM index links the consolidated Rules and Amendment No. 1 of 2025, reissued October 17, 2025. Current division, Fast Track allocation, practice directions and orders remain material. This guide does not assume a historical matter uses that edition.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)How are time and closure treated for ADGM accepted Part 18 offer payment?
ADGM Rule 6 counts days as clear days, excluding the start and an event-defined end. For periods of five days or less, Saturdays, Sundays and public holidays do not count. Actual month periods and operative events need their own source review. Current Rule 7(5), as amended on October 17, 2025, concerns a specified act whose period ends on a closed registry day, subject to the relevant practice direction. The amendment removed the old restriction to acts at the registry. Minimum notice, status and agreed caps remain distinct; no automatic final date is shown.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Why does ADGM accepted Part 18 offer payment show no final date?
The source period is retained, but the actual actual acceptance and applicable completion route need checking against your case. Check the actual documents and orders. No paid calculation is available.
ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5)Official sources and review
Provisions used (2)
| Provision | Purpose |
|---|---|
| ADGM Court Procedure Rules 2016, Part 18, rules 162(4) and 162(5) | Check the identified procedure, event, counting rule or qualification |
| ADGM Rules6-7 with Amendment No. 1 of 2025 paragraph4 | Check the identified procedure, event, counting rule or qualification |