England and Wales · Arbitration and court procedure
What period and facts govern refused material correction date in England and Wales?
The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
- Period
- The current section 70 court 28-day period uses subsection (3A)(c) where applicable
- Trigger
- Notification to that party of the tribunal’s decision not to grant the material application
- Rule
- Arbitration Act 1996 section 70
This refused material correction date guide uses retained current official Arbitration Act 1996 text and current Justice UK CPR and PD 62 pages. The 2025 Act section 12 and SI 2025/905 commenced the amended section 70 scheme on August 1, 2025. Section 17(4) of the 2025 Act preserves its specified precommencement exclusions; the actual arbitral and court commencement facts remain necessary.
Source guide · No automated date
Check the applicable procedure
Arbitration Act 1996 section 70. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. Establish the actual actor, event, agreed regime, court order and completion facts before relying on a final endpoint. This source guide provides no computed or paid date.
Arbitration Act 1996 section 70What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
What period and facts govern refused material correction date in England and Wales?
The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
Responsible actor. A court challenger whose material section 57 application was refused.
Notification to that party of the tribunal’s decision not to grant the material application
A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
A court challenger whose material section 57 application was refused. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
Arbitration Act 1996 section 70How does this provision count time?
- The current section 70 court 28-day period uses subsection (3A)(c) where applicable
- Issue the appropriate court challenge or appeal.
- A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
For refused material correction date, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less.
For refused material correction date, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
Arbitration Act 1996 section 70Which facts prevent one automatic date?
Arbitration Act 1996 section 70. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. Establish the actual actor, event, agreed regime, court order and completion facts before relying on a final endpoint. This source guide provides no computed or paid date.
A court challenger whose material section 57 application was refused has records establishing notification to that party of the tribunal’s decision not to grant the material application. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. Issue the appropriate court challenge or appeal. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. Establish all source facts before choosing a final date.
The proposed compliance period for refused material correction date meets a weekend, holiday or court-office closure. For refused material correction date, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less. For refused material correction date, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. Apply the actual counting regime to the particular act. Do not infer a uniform next-working-day extension.
A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. The actual branch facts are not established by the raw catalog period. Issue the appropriate court challenge or appeal. Establish the material facts or follow the actual order; this guide supplies no automatic date.
Which conditions and exceptions apply?
- Actual actor and completed procedural act
- A court challenger whose material section 57 application was refused. Issue the appropriate court challenge or appeal.
- Controlling event and applicable agreement or order
- Notification to that party of the tribunal’s decision not to grant the material application. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
- Source-specific counting and completion place
- For refused material correction date, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less. For refused material correction date, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
- A court challenger whose material section 57 application was refused. The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
- Refused material correction date concerns a court challenger whose material section 57 application was refused and issue the appropriate court challenge or appeal. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch. Award correction application addresses a separate procedural question and cannot establish this actor’s completed step.
What must the responsible actor complete?
Questions about this procedure
What period and facts govern refused material correction date in England and Wales?
What period applies to refused material correction date?
The current section 70 court 28-day period uses subsection (3A)(c) where applicable. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
Arbitration Act 1996 section 70Which actual event controls refused material correction date?
Notification to that party of the tribunal’s decision not to grant the material application. A court challenger whose material section 57 application was refused must establish that event from the actual request, award, service or court records.
Arbitration Act 1996 section 70What act completes refused material correction date?
Issue the appropriate court challenge or appeal. A pending request, an immaterial request and an unnotified refusal do not establish this particular applicable-date branch.
Arbitration Act 1996 section 70Is the tribunal’s refusal decision date the trigger?
The statutory language uses when the applicant or appellant was notified of the refusal. Identify the actual communication event.
Arbitration Act 1996 section 70Must the refused request have been material?
Yes. Subsections(3A)(c) and (3B) require a material correction or additional-award application, assessed against the actual court challenge.
Arbitration Act 1996 section 70Can equivalent agreed correction procedures matter?
Current section 70(9) includes equivalent recourse or acts under the parties’ section 57(1) agreement. The actual agreed process must be established.
Arbitration Act 1996 section 70Official sources and review
Provisions used (6)
| Provision | Purpose |
|---|---|
| Arbitration Act 1996 section 70 | Check the identified procedure, event, counting rule or qualification |
| Arbitration Act 1996 section 57 | Check the identified procedure, event, counting rule or qualification |
| Arbitration Act 2025 section 12 | Check the identified procedure, event, counting rule or qualification |
| Arbitration Act 2025 section 17 | Check the identified procedure, event, counting rule or qualification |
| CPR 2.8 | Check the identified procedure, event, counting rule or qualification |
| SI 2025/905 regulation 2 | Check the identified procedure, event, counting rule or qualification |