What period and facts govern rta £1,000 interim payment in England and Wales?

Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

5.0Rated by lawyers in California, London and Singapore“The platform is really easy to use.” — Michael B., California“The Evidence Record saved us time with our insurance on bankruptcy matters.” — Maria, London, UK“The most up-to-date service we could find.” — Li Chen, Singapore
Read why no date is calculated
Period
Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies
Trigger
Actual receipt of the Interim Settlement Pack
Rule
Low-value RTA Protocol paragraph 7.18
Low-value RTA Protocol paragraph 7.18

The rta £1,000 interim payment guide uses the maintained official low-value RTA Protocol acquired for this review. Scope, claim value, event history and any lawful variation remain actual case facts. Prior retained protocol originals remain separately preserved.

Source guide · No automated date

Check the applicable procedure

Low-value RTA Protocol paragraph 7.18. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18. Confirm the actual rta £1,000 interim payment facts before selecting an endpoint. This source guide provides no computed date or paid calculation.

Low-value RTA Protocol paragraph 7.18

What lawyers say

5.0
  • “The platform is really easy to use.”

    Michael B.Employment litigation attorney · California

  • “The Evidence Record saved us time with our insurance on bankruptcy matters.”

    MariaBankruptcy and commercial attorney · London, UK

  • “The most up-to-date service we could find.”

    Li ChenArbitration practitioner · Singapore

What period and facts govern rta £1,000 interim payment in England and Wales?

Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

Responsible actor. The defendant receiving a paragraph 7.13 request for a £1,000 interim payment.

Actual receipt of the Interim Settlement Pack

Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

The defendant receiving a paragraph 7.13 request for a £1,000 interim payment. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

Low-value RTA Protocol paragraph 7.18

How does this provision count time?

  1. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies
  2. Ensure the claimant receives the £1,000 within the applicable payment period.
  3. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

For rta £1,000 interim payment, paragraph 5.3 uses business days, excluding Saturday, Sunday, bank holidays, Good Friday and Christmas Day. Paragraph 5.4 starts response counting on the first business day after information was sent. Preserve the specific actual receipt of the Interim Settlement Pack.

For rta £1,000 interim payment, verify the actual England and Wales holiday dates and any permitted agreement. Paragraph 5.6 requires receipt of a cheque or transfer for payment, rather than final-day dispatch. The relevant protocol exception must be checked before selecting a payable date.

Low-value RTA Protocol paragraph 7.18

Which facts prevent one automatic date?

Low-value RTA Protocol paragraph 7.18. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18. Confirm the actual rta £1,000 interim payment facts before selecting an endpoint. This source guide provides no computed date or paid calculation.

ResultRead the operative provision and establish the applicable branch.

The defendant receiving a paragraph 7.13 request for a £1,000 interim payment has evidence of actual receipt of the Interim Settlement Pack. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Ensure the claimant receives the £1,000 within the applicable payment period. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18. Verify the complete rta £1,000 interim payment facts before relying on a final date.

A proposed rta £1,000 interim payment completion date meets a weekend, holiday or disputed delivery event. For rta £1,000 interim payment, paragraph 5.3 uses business days, excluding Saturday, Sunday, bank holidays, Good Friday and Christmas Day. Paragraph 5.4 starts response counting on the first business day after information was sent. Preserve the specific actual receipt of the Interim Settlement Pack. For rta £1,000 interim payment, verify the actual England and Wales holiday dates and any permitted agreement. Paragraph 5.6 requires receipt of a cheque or transfer for payment, rather than final-day dispatch. The relevant protocol exception must be checked before selecting a payable date. Establish the correct rta £1,000 interim payment event, counting route and effective completed act. This guide supplies no substitute calculated date.

Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18. The rta £1,000 interim payment source contract requires actual receipt of the Interim Settlement Pack. Ensure the claimant receives the £1,000 within the applicable payment period. Resolve this material branch before selecting a purported deadline.

Which conditions and exceptions apply?

Actor and completed rta £1,000 interim payment step
The defendant receiving a paragraph 7.13 request for a £1,000 interim payment. Ensure the claimant receives the £1,000 within the applicable payment period.
Controlling rta £1,000 interim payment event and exception
Actual receipt of the Interim Settlement Pack. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.
Counting and completion for rta £1,000 interim payment
For rta £1,000 interim payment, paragraph 5.3 uses business days, excluding Saturday, Sunday, bank holidays, Good Friday and Christmas Day. Paragraph 5.4 starts response counting on the first business day after information was sent. Preserve the specific actual receipt of the Interim Settlement Pack. For rta £1,000 interim payment, verify the actual England and Wales holiday dates and any permitted agreement. Paragraph 5.6 requires receipt of a cheque or transfer for payment, rather than final-day dispatch. The relevant protocol exception must be checked before selecting a payable date.
Low-value RTA Protocol paragraph 7.18
  • The defendant receiving a paragraph 7.13 request for a £1,000 interim payment. Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.
  • RTA £1,000 interim payment addresses ensure the claimant receives the £1,000 within the applicable payment period. RTA Stage 2 Settlement Pack has a separate event and purpose. The other procedure cannot establish this step’s completion or exceptions.

What must the responsible actor complete?

Questions about this procedure

What period and facts govern rta £1,000 interim payment in England and Wales?

What period governs rta £1,000 interim payment?

Paragraph 7.18 requires the £1,000 payment within ten business days of receiving the Interim Settlement Pack where paragraph 7.13 applies. Confirm the actual £1,000 request and pack receipt. Higher interim requests have separate provisions; their paragraph 7.24 certificate exception must not be imported into paragraph 7.18.

Low-value RTA Protocol paragraph 7.18

Which event controls rta £1,000 interim payment?

Actual receipt of the Interim Settlement Pack. The defendant receiving a paragraph 7.13 request for a £1,000 interim payment must preserve the supporting event records.

Low-value RTA Protocol paragraph 7.18

What completes rta £1,000 interim payment?

Ensure the claimant receives the £1,000 within the applicable payment period. The actual completion evidence must match the specified procedure.

Low-value RTA Protocol paragraph 7.18

Does an informal request for money establish this precise branch?

Paragraph 7.18 refers to paragraph 7.13 and receipt of the Interim Settlement Pack. Preserve the actual request and pack rather than infer those facts.

Low-value RTA Protocol paragraph 7.18

Can the defendant merely send the transfer instruction by the final day?

Paragraph 5.6 requires receipt of the cheque or transferred amount before the specified period ends.

Low-value RTA Protocol paragraph 5.6

Does the higher-payment CRU exception automatically replace this period?

No. Paragraphs 7.24 and 7.25 expressly concern payments under paragraph 7.19(1) or (3). They do not establish an automatic 30-day substitution for the paragraph 7.18 £1,000 payment.

Low-value RTA Protocol paragraph 7.24

Official sources and review

Provisions used (8)
Provisions used in this guide
ProvisionPurpose
Low-value RTA Protocol paragraph 7.18Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 7.13Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 7.24Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 7.25Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 5.3Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 5.6Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 5.4Check the identified procedure, event, counting rule or qualification
Low-value RTA Protocol paragraph 5.5Check the identified procedure, event, counting rule or qualification
Read the official controlling provision

Cookie preferences