England and Wales · Public law
What period and facts govern planning prior approval period in England and Wales?
Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
- Period
- Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations
- Trigger
- Receipt of the paragraph W application and required documents and fee by the local planning authority
- Rule
- Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph W
The planning prior approval period guide uses complete official response bodies retained with acquisition identities. Current legislative XML may contain temporal, territorial and transitional alternatives. The actual provision and case history require verification; this guide qualifies no new numeric model. The retained planning order or regulations apply to England. Welsh applications require their own applicable instrument.
Source guide · No automated date
Check the applicable procedure
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph W. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established. The planning prior approval period source guide provides no computed date or paid calculation.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WWhat lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
What period and facts govern planning prior approval period in England and Wales?
Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
Responsible actor. A developer within a permitted-development class that actually applies Part 3 paragraph W.
Receipt of the paragraph W application and required documents and fee by the local planning authority
Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
A developer within a permitted-development class that actually applies Part 3 paragraph W. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WHow does this provision count time?
- Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations
- Establish which statutory event permits the development to begin and comply with the applicable approved or submitted details.
- Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Preserve the source’s actual receipt, issue, beginning-with, day-after or before-event wording. An England-specific planning instrument cannot establish the corresponding Welsh procedure merely from a combined jurisdiction label.
For planning prior approval period, identify the statutory recipient and actual delivery or completed notice. A weekend or closed office does not independently establish permission, deemed consent or a statutory time extension.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WWhich facts prevent one automatic date?
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph W. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established. The planning prior approval period source guide provides no computed date or paid calculation.
A developer within a permitted-development class that actually applies Part 3 paragraph W has records of receipt of the paragraph W application and required documents and fee by the local planning authority. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Establish which statutory event permits the development to begin and comply with the applicable approved or submitted details. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established. Establish the complete planning prior approval period procedure before choosing an endpoint.
The proposed planning prior approval period step encounters a closed recipient, disputed delivery or an uncertain event. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Preserve the source’s actual receipt, issue, beginning-with, day-after or before-event wording. An England-specific planning instrument cannot establish the corresponding Welsh procedure merely from a combined jurisdiction label. For planning prior approval period, identify the statutory recipient and actual delivery or completed notice. A weekend or closed office does not independently establish permission, deemed consent or a statutory time extension. Establish effective planning prior approval period completion and source applicability. No assumed closure extension or substitute date is computed.
Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established. Receipt of the paragraph W application and required documents and fee by the local planning authority. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Establish which statutory event permits the development to begin and comply with the applicable approved or submitted details. Preserve this planning prior approval period qualification rather than converting incomplete facts into a final date.
Which conditions and exceptions apply?
- Actor and completed planning prior approval period step
- A developer within a permitted-development class that actually applies Part 3 paragraph W. Establish which statutory event permits the development to begin and comply with the applicable approved or submitted details.
- Operative planning prior approval period event and branch
- Receipt of the paragraph W application and required documents and fee by the local planning authority. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
- Counting and completion of planning prior approval period
- Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Preserve the source’s actual receipt, issue, beginning-with, day-after or before-event wording. An England-specific planning instrument cannot establish the corresponding Welsh procedure merely from a combined jurisdiction label. For planning prior approval period, identify the statutory recipient and actual delivery or completed notice. A weekend or closed office does not independently establish permission, deemed consent or a statutory time extension.
- A developer within a permitted-development class that actually applies Part 3 paragraph W. Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
- Planning prior approval period concerns establish which statutory event permits the development to begin and comply with the applicable approved or submitted details. The receipt of the paragraph W application and required documents and fee by the local planning authority establishes this procedure’s source event. A different remedy, notice recipient or statutory regime requires its own period and completed-act analysis.
What must the responsible actor complete?
Questions about this procedure
What period and facts govern planning prior approval period in England and Wales?
What period governs planning prior approval period?
Paragraph W(11) includes expiry of fifty-six days after receipt without the prescribed notification, alongside earlier written determinations. Fifty-six days is not a universal GPDO determination period. Actual class eligibility, limitations and paragraph W procedure must be established.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WWhich event controls planning prior approval period?
Receipt of the paragraph W application and required documents and fee by the local planning authority. Preserve the actual event and its source evidence.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WWhat completes planning prior approval period?
Establish which statutory event permits the development to begin and comply with the applicable approved or submitted details. A developer within a permitted-development class that actually applies Part 3 paragraph W must establish that particular completed step.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WDoes every permitted-development class use fifty-six days?
No. The retained paragraph W governs the identified Part 3 procedure. Other classes and Parts require their own conditions and periods.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WCan development begin immediately upon applying for prior approval?
Paragraph W(11) requires the relevant written notice or the prescribed fifty-six-day expiry without notification. Other substantive conditions remain applicable.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WDoes no response remove every development condition?
Paragraph W(12) still requires development in accordance with the relevant approved or submitted details, unless the authority and developer agree otherwise in writing.
Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph WOfficial sources and review
Provisions used (1)
| Provision | Purpose |
|---|---|
| Town and Country Planning (General Permitted Development) (England) Order 2015 Schedule 2 Part 3 paragraph W | Check the identified procedure, event, counting rule or qualification |