When must an Upper Tribunal Lands permission application be received after refusal below?

The applicant whose lower tribunal refused permission or refused to admit the permission application. Received by the Upper Tribunal no later than 14 days after the refusal notice was sent. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.

5.0Rated by lawyers in California, London and Singapore“The platform is really easy to use.” — Michael B., California“The Evidence Record saved us time with our insurance on bankruptcy matters.” — Maria, London, UK“The most up-to-date service we could find.” — Li Chen, Singapore
Calculate my deadline
Period
Received by the Upper Tribunal no later than 14 days after the refusal notice was sent
Trigger
The date the lower tribunal sent its qualifying refusal notice to the applicant
Rule
Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12
Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12. Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.

Free calculator · No account needed

Calculate your deadline

Loading calculator…

What lawyers say

5.0
  • “The platform is really easy to use.”

    Michael B.Employment litigation attorney · California

  • “The Evidence Record saved us time with our insurance on bankruptcy matters.”

    MariaBankruptcy and commercial attorney · London, UK

  • “The most up-to-date service we could find.”

    Li ChenArbitration practitioner · Singapore

When must an Upper Tribunal Lands permission application be received after refusal below?

The applicant whose lower tribunal refused permission or refused to admit the permission application. Received by the Upper Tribunal no later than 14 days after the refusal notice was sent. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.

Responsible actor. The applicant whose lower tribunal refused permission or refused to admit the permission application.

The date the lower tribunal sent its qualifying refusal notice to the applicant

Actual lower permission application and refusal or non-admission established

Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

How does this provision count time?

  1. Exclude the qualifying notice-sending date and count 14 calendar days. Rule 12 permits the act on the next working day at a closed endpoint and requires completion by 5PM, unlike the First-tier rule’s before-5PM wording.
  2. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber
  3. The Lands Chamber must receive the ordinary renewed permission application by 5PM under rule 12. This inclusive clock boundary differs from the First-tier Tribunal’s before-5PM requirement. No December vacation exclusion is imported; unresolved regional holidays prevent a completion date.

Exclude the qualifying notice-sending date and count 14 calendar days. Rule 12 permits the act on the next working day at a closed endpoint and requires completion by 5PM, unlike the First-tier rule’s before-5PM wording.

The Lands Chamber must receive the ordinary renewed permission application by 5PM under rule 12. This inclusive clock boundary differs from the First-tier Tribunal’s before-5PM requirement. No December vacation exclusion is imported; unresolved regional holidays prevent a completion date.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

What do independently checked examples show?

Fictitious example

Fictitious actual source event. The date the lower tribunal sent its qualifying refusal notice to the applicant established on Tuesday, October 13, 2026. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. All selected source conditions are established unless this scenario expressly refuses them.

Example counting steps
StepWhat is countedDate
Example 1. Ordinary established factsFictitious actual source event. The date the lower tribunal sent its qualifying refusal notice to the applicant established on Tuesday, October 13, 2026. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. All selected source conditions are established unless this scenario expressly refuses them. Independently derived with Python calendar correspondence or counted calendar dates, without importing the application helper or engine.October 27, 2026 by 5PM Europe/London. Inclusive clock boundary 2026-10-27T17:00:00.000Z.
Example 2. Closed-day boundaryFictitious actual source event. The date the lower tribunal sent its qualifying refusal notice to the applicant established on Saturday, December 12, 2026. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. All selected source conditions are established unless this scenario expressly refuses them. Independently derived with Python calendar correspondence or counted calendar dates, without importing the application helper or engine.December 29, 2026 by 5PM Europe/London. Inclusive clock boundary 2026-12-29T17:00:00.000Z.
Example 3. Material procedural branchFictitious actual source event. The date the lower tribunal sent its qualifying refusal notice to the applicant established on Tuesday, October 13, 2026. Provide the signed and dated application, required copies, documents and payable fee to the Upper Tribunal Lands Chamber. All selected source conditions are established unless this scenario expressly refuses them. Independently derived with Python calendar correspondence or counted calendar dates, without importing the application helper or engine.The lower permission refusal or non-admission branch is not established. The limited-grounds route needs separate jurisdictional qualification.
Example resultOctober 27, 2026 by 5PM Europe/London. Inclusive clock boundary 2026-10-27T17:00:00.000Z.

Fictitious established facts. These examples do not establish eligibility, effective service, relief or a direction.

Try these dates in the calculator

Which conditions and exceptions apply?

Applicable source condition 1
Actual lower permission application and refusal or non-admission established
Applicable source condition 2
Actual refusal-notice sending date established
Applicable source condition 3
Required documents, copies, fee and no different operative period established
Counting and completion
Exclude the qualifying notice-sending date and count 14 calendar days. Rule 12 permits the act on the next working day at a closed endpoint and requires completion by 5PM, unlike the First-tier rule’s before-5PM wording. The Lands Chamber must receive the ordinary renewed permission application by 5PM under rule 12. This inclusive clock boundary differs from the First-tier Tribunal’s before-5PM requirement. No December vacation exclusion is imported; unresolved regional holidays prevent a completion date.
Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12
  • Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.
  • Rule 21(1) requires the prior permission application and its refusal or non-admission. Rule 21(2) also references a notice granting only limited grounds. That additional branch requires its jurisdiction to be established separately before this ordinary-refusal model is used.

What must the responsible actor complete?

Questions about this procedure

When must an Upper Tribunal Lands permission application be received after refusal below?

Is this another 28-day period?

No. Rule 21(2) specifies 14 days for the application received by the Upper Tribunal Lands Chamber.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

Must permission have been sought below first?

Rule 21(1) ordinarily requires an application to the tribunal that made the challenged decision and refusal or non-admission there.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

Does receipt of the refusal letter start the period?

The rule uses when the lower tribunal sent the notice to the applicant.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

What if permission was granted on limited grounds?

Rule 21(2) references the limited-grounds notification. Establish the jurisdiction and precise further-permission branch separately from this ordinary-refusal model.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

What documents accompany the application?

Rule 21(4) requires the decision, separate reasons, lower refusal notice, other relied-on documents and the payable fee. Subsection (7) requires sufficient copies for the respondent.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

Is the Lands Chamber rule the general Upper Tribunal rule?

No. The Lands Chamber uses the 2010 Rules, including rule 12’s by-5PM completion requirement. Do not substitute the 2008 Rules or another chamber’s calendar.

Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12

Official sources and review

Provisions used (2)
Provisions used in this guide
ProvisionPurpose
Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rr.21(1)–(7), 12Check the identified procedure, event, counting rule or qualification
Tribunal Procedure (Upper Tribunal) (Lands Chamber) Rules 2010, rules 5(3)(a), 12 and 13Check the identified procedure, event, counting rule or qualification