England and Wales · Public law
What period and facts govern saved pcr electronic standstill in England and Wales?
Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
- Period
- Standstill ends at midnight at the end of the tenth day after the relevant last sending date
- Trigger
- The last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices
- Rule
- Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87
The saved pcr electronic standstill guide uses complete official response bodies retained with acquisition identities. Current legislative XML may contain temporal, territorial and transitional alternatives. The actual provision and case history require verification; this guide qualifies no new numeric model. The current revoked PCR XML is preserved separately from the February 23, 2025 edition. Current SI 2024/716 regulation 5 supplies the actual saving conditions; the Procurement Act began its main regime on February 24, 2025.
Source guide · No automated date
Check the applicable procedure
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required. The saved pcr electronic standstill source guide provides no computed date or paid calculation.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
What period and facts govern saved pcr electronic standstill in England and Wales?
Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
Responsible actor. A contracting authority within a procurement saved under the Public Contracts Regulations 2015.
The last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices
All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
A contracting authority within a procurement saved under the Public Contracts Regulations 2015. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87How does this provision count time?
- Standstill ends at midnight at the end of the tenth day after the relevant last sending date
- Do not enter the contract or conclude the framework before standstill ends.
- All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
Standstill ends at midnight at the end of the tenth day after the relevant last sending date. The saved regulations distinguish beginning-with knowledge, day-after notification and express midnight standstill endpoints. Regulation 2(4) ordinarily carries a forward-counted nonworking final day to the next working day. The new Act’s eight-working-day model is not interchangeable.
For saved pcr electronic standstill, retain the relevant electronic, other-method, publication and receipt history. Establish the saving condition and the applicable statutory time computation before relying on a closure or court extension.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87Which facts prevent one automatic date?
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required. The saved pcr electronic standstill source guide provides no computed date or paid calculation.
A contracting authority within a procurement saved under the Public Contracts Regulations 2015 has records of the last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. Do not enter the contract or conclude the framework before standstill ends. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required. Establish the complete saved pcr electronic standstill procedure before choosing an endpoint.
The proposed saved pcr electronic standstill step encounters a closed recipient, disputed delivery or an uncertain event. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. The saved regulations distinguish beginning-with knowledge, day-after notification and express midnight standstill endpoints. Regulation 2(4) ordinarily carries a forward-counted nonworking final day to the next working day. The new Act’s eight-working-day model is not interchangeable. For saved pcr electronic standstill, retain the relevant electronic, other-method, publication and receipt history. Establish the saving condition and the applicable statutory time computation before relying on a closure or court extension. Establish effective saved pcr electronic standstill completion and source applicability. No assumed closure extension or substitute date is computed.
All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required. The last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. Do not enter the contract or conclude the framework before standstill ends. Preserve this saved pcr electronic standstill qualification rather than converting incomplete facts into a final date.
Which conditions and exceptions apply?
- Actor and completed saved pcr electronic standstill step
- A contracting authority within a procurement saved under the Public Contracts Regulations 2015. Do not enter the contract or conclude the framework before standstill ends.
- Operative saved pcr electronic standstill event and branch
- The last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
- Counting and completion of saved pcr electronic standstill
- Standstill ends at midnight at the end of the tenth day after the relevant last sending date. The saved regulations distinguish beginning-with knowledge, day-after notification and express midnight standstill endpoints. Regulation 2(4) ordinarily carries a forward-counted nonworking final day to the next working day. The new Act’s eight-working-day model is not interchangeable. For saved pcr electronic standstill, retain the relevant electronic, other-method, publication and receipt history. Establish the saving condition and the applicable statutory time computation before relying on a closure or court extension.
- A contracting authority within a procurement saved under the Public Contracts Regulations 2015. Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
- Saved PCR electronic standstill concerns do not enter the contract or conclude the framework before standstill ends. The the last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices establishes this procedure’s source event. A different remedy, notice recipient or statutory regime requires its own period and completed-act analysis.
What must the responsible actor complete?
Questions about this procedure
What period and facts govern saved pcr electronic standstill in England and Wales?
What period governs saved pcr electronic standstill?
Standstill ends at midnight at the end of the tenth day after the relevant last sending date. All-electronic, all-other and mixed-method notices have distinct formulas. Actual saving facts, recipients and sending history are required.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87Which event controls saved pcr electronic standstill?
The last sending of the regulation 86 notices where all relevant operators receive fax or electronic notices. Preserve the actual event and its source evidence.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87What completes saved pcr electronic standstill?
Do not enter the contract or conclude the framework before standstill ends. A contracting authority within a procurement saved under the Public Contracts Regulations 2015 must establish that particular completed step.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87Does the first electronic award notice start this standstill?
Regulation 87(4) uses the last sending date where relevant notices are sent on different dates. Preserve all required sending records.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87What if some operators received notices by another method?
Regulation 87(5) uses the later of the electronic endpoint and the prescribed other-method endpoint. The simple all-electronic branch is insufficient.
Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87Can the saved ten-day standstill be used for every new award?
No. The commencement and saving regulations determine whether the old regime continues. Procurement Act standstill instead uses its own eight-working-day structure.
Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 regulation 5Official sources and review
Provisions used (4)
| Provision | Purpose |
|---|---|
| Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 87 | Check the identified procedure, event, counting rule or qualification |
| Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 86 | Check the identified procedure, event, counting rule or qualification |
| Public Contracts Regulations 2015, edition immediately before February 24, 2025 regulation 2 | Check the identified procedure, event, counting rule or qualification |
| Procurement Act 2023 (Commencement No. 3 and Transitional and Saving Provisions) Regulations 2024 regulation 5 | Check the identified procedure, event, counting rule or qualification |