United States · New York civil procedure
When must a New York summons be served after filing?
CPLR 306-b ordinarily requires service within 120 days after commencement. A four-month-or-shorter limitation period has a separate service branch.
- Period
- 120 calendar days
- Trigger
- Actual filing that commenced this action or special proceeding
- Rule
- CPLR 306-b
Current official section, website revision from 2026-04-24, reviewed. The revision label is not an inferred effective date.
Free calculator · No account needed
Calculate your deadline
Loading calculator…
What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
Which event starts the CPLR 306-b period?
Identify the accepted filing that commenced this particular action under CPLR 304. Use the clerk’s filing record, not drafting, index-number purchase alone or later service.
Establish that the ordinary 120-day branch applies. This preset excludes the four-month-or-shorter limitation branch, election proceedings, third-party practice and commencement through a court’s emergency signing order.
Responsible actor. The plaintiff or petitioner arranging valid service on this defendant. An ordinary CPLR 304 filing and the 120-day CPLR 306-b branch only. No short limitation branch, third-party summons, exceptional commencement, granted extension or different order is assumed.
CPLR 306-bHow is this service or filing period counted?
- Identify the accepted filing that commenced this particular action under CPLR 304. Use the clerk’s filing record, not drafting, index-number purchase alone or later service.
- Establish that the ordinary 120-day branch applies. This preset excludes the four-month-or-shorter limitation branch, election proceedings, third-party practice and commencement through a court’s emergency signing order.
- Exclude the established event day and count 120 calendar days forward. Intermediate weekends and public holidays count. General Construction Law 25-a permits the next succeeding business day for a closed final statutory day.
- Complete legally valid service of the required initiating papers on this defendant. Preserve the process-server evidence and any required proof filing. Filing the action alone does not serve the defendant.
General Construction Law 20 excludes the established event day. Intermediate Saturdays, Sundays and public holidays count in these fifteen-, twenty-, sixty- and 120-day calendar periods. Section 25-a permits the next succeeding business day for a closed final statutory day and expressly includes a period before which an act is required. The backward notice-to-admit boundary still requires the actual trial date and separate opening condition.
The independently derived 2026 and 2027 calendar follows General Construction Law 24 and Election Law 8-100. It includes Lincoln’s Birthday, Flag Day on the second Sunday in June, Juneteenth, general election day and the other specified holidays. Section 24 adds the next day when a listed holiday falls on Sunday, except Flag Day. A Saturday holiday is not automatically observed on Friday under this provision. Additional appointed holidays and actual court or system closures require separate proof.
These calculators cover established events and final dates within January 1, 2026 through December 31, 2027. They require the disclosed statutory branch, independently valid service, no unsupported method addition, no different actual court order and no additional closure. The backward notice-to-admit preset requires an actual open-day trial date and an independently established opening condition. Earlier editions, the 2020 executive-order toll and dates beyond the retained calendar require separate review and receive no computed or paid date. This software coverage boundary does not establish that an actual act is late.
General Construction Law 20, calendar days and exact two-day exceptionWhat does the independently derived example establish?
Fictitious example
An ordinary CPLR 304 filing and the 120-day CPLR 306-b branch only. No short limitation branch, third-party summons, exceptional commencement, granted extension or different order is assumed. Fictitious established event on the input date. An ordinary CPLR 304 filing and the 120-day CPLR 306-b branch only. No short limitation branch, third-party summons, exceptional commencement, granted extension or different order is assumed.
| Step | What is counted | Date |
|---|---|---|
| Established procedural event | Actual filing that commenced this action or special proceeding | September 1, 2026 |
| Disclosed statutory component | 120 calendar days | Wednesday, December 30, 2026 |
Fictitious established facts. The result does not prove valid service, the required exception, actual filing, preserved jurisdiction or a granted court extension. The applicable hour and actual court directions remain separate checks.
Try these dates in the calculatorWhich facts change this procedural requirement?
- Short limitation period
- Except for Election Law proceedings, an applicable limitation period of four months or less uses service no later than fifteen days after that period expires. Establish that expiry separately.
- Actual commencement
- CPLR 304 specifies filing of a summons and complaint or summons with notice for an action, and a petition for a special proceeding. Its exceptional signing-order branch has different facts and is excluded.
- Valid initial service
- CPLR 2103 concerns papers in a pending action. Its mail response additions do not add days to this filing-based initial-service period. The proper method for serving this defendant remains a separate legal check.
- Discretionary extension
- CPLR 306-b gives the court good-cause and interest-of-justice grounds. Braun identifies them as independent standards and explains the broader balancing test. No court extension is automatically added.
- Edition and calendar coverage
- These calculators cover established events and final dates within January 1, 2026 through December 31, 2027. They require the disclosed statutory branch, independently valid service, no unsupported method addition, no different actual court order and no additional closure. The backward notice-to-admit preset requires an actual open-day trial date and an independently established opening condition. Earlier editions, the 2020 executive-order toll and dates beyond the retained calendar require separate review and receive no computed or paid date. This software coverage boundary does not establish that an actual act is late.
- An ordinary CPLR 304 filing and the 120-day CPLR 306-b branch only. No short limitation branch, third-party summons, exceptional commencement, granted extension or different order is assumed.
- The selected date supplies only the disclosed statutory branch. It does not validate the facts or authorize an unmodeled alternative.
Which documents, completed acts and proof should be retained?
Questions about CPLR 306-b
When must a New York summons be served after filing?
Does the clock begin when the defendant receives the summons?
No. This 120-day branch starts when the action or proceeding is commenced. Valid service must occur within that separate period.
CPLR 306-bDo I receive 120 days if my limitation period is four months?
The statute provides a separate fifteen-day-after-expiry branch for that classification, except Election Law proceedings. This calculator does not decide the limitation period.
CPLR 306-bIs dismissal automatic at day 121?
Section 306-b addresses a court decision upon motion and permits an extension on its stated grounds. This calendar does not establish that dismissal occurred.
CPLR 306-bOfficial New York procedural, counting and filing sources
Provisions used (10)
| Provision | Purpose |
|---|---|
| CPLR 306-b | The particular actor, event, period and required act |
| CPLR 304 | Actual commencement |
| CPLR 2103 | Valid initial service |
| State of New York Mtge. Agency v Braun, 182 AD3d 63, 66-67 (2020) | Discretionary extension |
| General Construction Law 20, calendar days and exact two-day exception | Event-day exclusion and intermediate calendar days |
| General Construction Law 24, public holidays | Statutory public holidays and Sunday observance |
| General Construction Law 25-a, next succeeding business day | Closed final statutory day and next succeeding business day |
| Election Law 8-100(1)(c), general election day | General election day in the statutory calendar |
| CPLR 2103, valid service and specified response additions | Valid initial service |
| 22 NYCRR 202.5-b(d), (f), (h), (i) | Electronic filing and participating-party service events; initial service remains separate |