United States · New York civil procedure
When must a motion for permission to appeal be made?
CPLR 5513(b) uses thirty days after qualifying service with notice of entry, including its stated lower-court denial and own-service branches.
- Period
- 30 days
- Trigger
- Valid personal service of the qualifying judgment, order or lower-court leave-denial order with notice of entry
- Rule
- CPLR 5513(b), (d)
Current official provision, website revision from 2014-09-22. Reviewed. A revision label is not an inferred effective date.
Free calculator · No account needed
Calculate your deadline
Loading calculator…
What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
Which event starts the CPLR 5513(b), (d) requirement?
Identify whether the served document is the original determination or a proper denial of permission by the court whose determination is under review.
Retain the document, written notice of entry and valid personal service. Check the applicant’s own qualifying service.
Responsible actor. The party seeking otherwise available permission to appeal. CPLR 5513(b)’s established personal-service branch, with the proper leave court and document independently identified.
CPLR 5513(b), (d)How is the stated statutory period counted?
- Identify whether the served document is the original determination or a proper denial of permission by the court whose determination is under review.
- Retain the document, written notice of entry and valid personal service. Check the applicant’s own qualifying service.
- Exclude the established event day and count every intermediate calendar day under GCL 20.
- Make the permission motion in the correct court. Complete the applicable motion service and filing rather than assuming a notice of appeal supplies permission.
GCL 20 excludes the established event day. These five-, ten-, fifteen-, twenty-, twenty-one-, thirty-, sixty- and ninety-day periods count intermediate calendar days. GCL 30 uses the corresponding calendar-month day, or the final day of a shorter month. GCL 58 defines a year as twelve months. GCL 25-a permits the next succeeding business day when the statutory final day is closed and expressly includes periods before which an act is required. The actual hearing or entry time and any different court direction remain separate checks. The independent calendar follows GCL 24 and Election Law 8-100. It includes Lincoln’s Birthday, the second Sunday in June as Flag Day, Juneteenth and general election day. GCL 24 adds the following day for a listed Sunday holiday except Flag Day. It does not generally move a Saturday holiday to Friday. Dates after 2027 are projections of the reviewed standing statute through 2033, not proof of future court openings. Check amendments, additional appointed holidays and actual closures separately.
The scoped calculators accept independently established events in 2026 and 2027 and projected final dates through 2033. They require the particular disclosed branch, no unsupported service-method addition, no unmodeled toll, no different actual court order and no additional closure. Earlier editions, historical tolls and outside dates require separate review and receive no computed or paid date. This software boundary does not establish that an act is legally late.
General Construction Law 20, event-day exclusionWhat does the independently derived example establish?
Fictitious example
CPLR 5513(b)’s established personal-service branch, with the proper leave court and document independently identified. Fictitious established facts. CPLR 5513(b)’s established personal-service branch, with the proper leave court and document independently identified.
| Step | What is counted | Date |
|---|---|---|
| Established procedural event | Valid personal service of the qualifying judgment, order or lower-court leave-denial order with notice of entry | September 1, 2026 |
| Disclosed statutory component | 30 days | Thursday, October 1, 2026 |
Fictitious established facts. The date does not prove classification, valid service, jurisdiction, completed filing, a granted motion or an extension. Any earlier competing boundary, actual hour and future-calendar qualification still applies.
Try these dates in the calculatorWhich facts change this requirement?
- Proper denial
- A qualifying lower-court denial order with notice of entry can supply the event specified in subdivision (b).
- Own service and method
- Own qualifying service starts time. Mail and overnight additions under subdivision (d) require separate inputs.
- Available relief
- The motion must otherwise be available. Section 5514(c) limits extensions rather than giving general discretionary extra time.
- Edition and projected calendar
- The scoped calculators accept independently established events in 2026 and 2027 and projected final dates through 2033. They require the particular disclosed branch, no unsupported service-method addition, no unmodeled toll, no different actual court order and no additional closure. Earlier editions, historical tolls and outside dates require separate review and receive no computed or paid date. This software boundary does not establish that an act is legally late.
- CPLR 5513(b)’s established personal-service branch, with the proper leave court and document independently identified.
- Use only the disclosed statutory component. Establish every omitted branch separately.
Which completed acts and evidence should be retained?
Questions about CPLR 5513(b), (d)
When must a motion for permission to appeal be made?
Do I automatically receive permission after filing?
No. A judicial grant is required.
CPLR 5513(b), (d)Does every denial by every court restart thirty days?
No. Subdivision (b) describes the denial by the court whose determination is sought to be reviewed.
CPLR 5513(b), (d)Can I use the appeal-as-of-right page instead?
Only an otherwise available appeal as of right uses that procedure. Permission has its own motion and court requirements.
CPLR 5513(b), (d)Official procedural, counting and completion sources
Provisions used (11)
| Provision | Purpose |
|---|---|
| CPLR 5513(b), (d) | The particular actor, event, period and required act |
| CPLR 5514 | Available relief |
| CPLR 2211 | Additional procedural event or qualification |
| 22 NYCRR 202.5-b(d), (f), (h), (i) | Branch-specific service or filing completion |
| CPLR 2103, party-paper service and specified method additions | Branch-specific service or filing completion |
| General Construction Law 20, event-day exclusion | Event-day exclusion |
| General Construction Law 30, corresponding calendar month | Corresponding month day and shorter-month end |
| General Construction Law 58, statutory year | Statutory year and leap-year treatment |
| General Construction Law 24, public holidays | Statutory public holidays |
| General Construction Law 25-a, closed final day | Closed final statutory day |
| Election Law 8-100(1)(c), general election day | General election day |