When must a New York post-trial motion be made?
CPLR 4405 requires a post-trial motion before the trial judge within fifteen days after the applicable decision, verdict or jury discharge.
- Period
- 15 days
- Trigger
- Applicable actual decision, verdict or jury discharge
- Rule
- CPLR 4405
Current official provision, website revision from 2014-09-22. Reviewed. A revision label is not an inferred effective date.
Free calculator · No account needed
Calculate your deadline
Loading calculator…
What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
Which event starts the CPLR 4405 requirement?
Identify the event applicable to the particular requested relief. Preserve the verdict, decision or jury-discharge record.
Do not substitute later judgment entry or its service for the applicable trial event.
Responsible actor. The party seeking post-trial relief under CPLR article 44. The established CPLR article 44 trial event and a motion before the judge who presided, before appellate argument or submission.
CPLR 4405How is the stated statutory period counted?
- Identify the event applicable to the particular requested relief. Preserve the verdict, decision or jury-discharge record.
- Do not substitute later judgment entry or its service for the applicable trial event.
- Exclude the established event day and count every intermediate calendar day under GCL 20.
- Make the motion before the trial judge. For a noticed motion, CPLR 2211 uses service of its notice or order to show cause. Complete the separate required filing.
GCL 20 excludes the established event day. These five-, ten-, fifteen-, twenty-, twenty-one-, thirty-, sixty- and ninety-day periods count intermediate calendar days. GCL 30 uses the corresponding calendar-month day, or the final day of a shorter month. GCL 58 defines a year as twelve months. GCL 25-a permits the next succeeding business day when the statutory final day is closed and expressly includes periods before which an act is required. The actual hearing or entry time and any different court direction remain separate checks. The independent calendar follows GCL 24 and Election Law 8-100. It includes Lincoln’s Birthday, the second Sunday in June as Flag Day, Juneteenth and general election day. GCL 24 adds the following day for a listed Sunday holiday except Flag Day. It does not generally move a Saturday holiday to Friday. Dates after 2027 are projections of the reviewed standing statute through 2033, not proof of future court openings. Check amendments, additional appointed holidays and actual closures separately.
The scoped calculators accept independently established events in 2026 and 2027 and projected final dates through 2033. They require the particular disclosed branch, no unsupported service-method addition, no unmodeled toll, no different actual court order and no additional closure. Earlier editions, historical tolls and outside dates require separate review and receive no computed or paid date. This software boundary does not establish that an act is legally late.
General Construction Law 20, event-day exclusionWhat does the independently derived example establish?
Fictitious example
The established CPLR article 44 trial event and a motion before the judge who presided, before appellate argument or submission. Fictitious established facts. The established CPLR article 44 trial event and a motion before the judge who presided, before appellate argument or submission.
| Step | What is counted | Date |
|---|---|---|
| Established procedural event | Applicable actual decision, verdict or jury discharge | September 1, 2026 |
| Disclosed statutory component | 15 days | Wednesday, September 16, 2026 |
Fictitious established facts. The date does not prove classification, valid service, jurisdiction, completed filing, a granted motion or an extension. Any earlier competing boundary, actual hour and future-calendar qualification still applies.
Try these dates in the calculatorWhich facts change this requirement?
- Trial judge
- Section 4405 requires the judge who presided at the trial.
- Appellate cutoff
- The court has no power under this provision to grant relief after argument or submission of an appeal from the final judgment.
- Relief grounds
- CPLR 4404 distinguishes jury and nonjury trial relief. A timely date does not establish entitlement.
- Edition and projected calendar
- The scoped calculators accept independently established events in 2026 and 2027 and projected final dates through 2033. They require the particular disclosed branch, no unsupported service-method addition, no unmodeled toll, no different actual court order and no additional closure. Earlier editions, historical tolls and outside dates require separate review and receive no computed or paid date. This software boundary does not establish that an act is legally late.
- The established CPLR article 44 trial event and a motion before the judge who presided, before appellate argument or submission.
- Use only the disclosed statutory component. Establish every omitted branch separately.
Which completed acts and evidence should be retained?
Questions about CPLR 4405
When must a New York post-trial motion be made?
Do fifteen days begin at judgment entry?
Section 4405 lists decision, verdict or jury discharge. Identify the applicable event.
CPLR 4405Can I simply file without serving?
A motion on notice is made by completed service under CPLR 2211.
CPLR 2211Does a timely motion guarantee a new trial?
No. The appropriate grounds and judicial decision remain separate.
CPLR 4405Official procedural, counting and completion sources
Provisions used (11)
| Provision | Purpose |
|---|---|
| CPLR 4405 | The particular actor, event, period and required act |
| CPLR 4404 | Relief grounds |
| CPLR 2211 | Additional procedural event or qualification |
| 22 NYCRR 202.5-b(d), (f), (h), (i) | Branch-specific service or filing completion |
| CPLR 2103, party-paper service and specified method additions | Branch-specific service or filing completion |
| General Construction Law 20, event-day exclusion | Event-day exclusion |
| General Construction Law 30, corresponding calendar month | Corresponding month day and shorter-month end |
| General Construction Law 58, statutory year | Statutory year and leap-year treatment |
| General Construction Law 24, public holidays | Statutory public holidays |
| General Construction Law 25-a, closed final day | Closed final statutory day |
| Election Law 8-100(1)(c), general election day | General election day |