What period and facts govern respondent permission-appeal notice in England and Wales?
Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
- Period
- Within 21 days after the required acknowledgment date
- Trigger
- The date on which that respondent was required to acknowledge service
- Rule
- PD 62 paragraph 12.7
This respondent permission-appeal notice guide uses the retained current Justice UK PD 62 paragraph 12.7 text. Actual case orders and specialist-court directions must be checked. Where the underlying claim challenges an award, establish the 2025 Act transition and the source-supported section 70 applicable date separately.
Source guide · No automated date
Check the applicable procedure
PD 62 paragraph 12.7. Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Establish the actual actor, event, agreed regime, court order and completion facts before relying on a final endpoint. This source guide provides no computed or paid date.
PD 62 paragraph 12.7What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
What period and facts govern respondent permission-appeal notice in England and Wales?
Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
Responsible actor. A respondent opposing permission to appeal an arbitration award.
The date on which that respondent was required to acknowledge service
Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
A respondent opposing permission to appeal an arbitration award. Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
PD 62 paragraph 12.7How does this provision count time?
- Within 21 days after the required acknowledgment date
- File and serve the respondent’s notice with its compliant skeleton argument.
- Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
For respondent permission-appeal notice, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less.
For respondent permission-appeal notice, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
PD 62 paragraph 12.7Which facts prevent one automatic date?
PD 62 paragraph 12.7. Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Establish the actual actor, event, agreed regime, court order and completion facts before relying on a final endpoint. This source guide provides no computed or paid date.
A respondent opposing permission to appeal an arbitration award has records establishing the date on which that respondent was required to acknowledge service. Within 21 days after the required acknowledgment date. File and serve the respondent’s notice with its compliant skeleton argument. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Establish all source facts before choosing a final date.
The proposed compliance period for respondent permission-appeal notice meets a weekend, holiday or court-office closure. For respondent permission-appeal notice, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less. For respondent permission-appeal notice, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Apply the actual counting regime to the particular act. Do not infer a uniform next-working-day extension.
Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Within 21 days after the required acknowledgment date. The actual branch facts are not established by the raw catalog period. File and serve the respondent’s notice with its compliant skeleton argument. Establish the material facts or follow the actual order; this guide supplies no automatic date.
Which conditions and exceptions apply?
- Actual actor and completed procedural act
- A respondent opposing permission to appeal an arbitration award. File and serve the respondent’s notice with its compliant skeleton argument.
- Controlling event and applicable agreement or order
- The date on which that respondent was required to acknowledge service. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
- Source-specific counting and completion place
- For respondent permission-appeal notice, section 80(4) and (5) separates court issue from service and applies court counting rules to statutory court time limits. CPR 2.8 computes day periods as clear days and omits specified nonworking days only for periods of five days or less. For respondent permission-appeal notice, CPR 2.8(5) addresses an act at a court office whose final day is a closure day. It does not automatically move service on another party, erase required intervening clear days, or lift the enforcement restriction. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
- A respondent opposing permission to appeal an arbitration award. Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
- Respondent permission-appeal notice concerns a respondent opposing permission to appeal an arbitration award and file and serve the respondent’s notice with its compliant skeleton argument. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions. Applicant permission-appeal reply addresses a separate procedural question and cannot establish this actor’s completed step.
What must the responsible actor complete?
Questions about this procedure
What period and facts govern respondent permission-appeal notice in England and Wales?
What period applies to respondent permission-appeal notice?
Within 21 days after the required acknowledgment date. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
PD 62 paragraph 12.7Which actual event controls respondent permission-appeal notice?
The date on which that respondent was required to acknowledge service. A respondent opposing permission to appeal an arbitration award must establish that event from the actual request, award, service or court records.
PD 62 paragraph 12.7What act completes respondent permission-appeal notice?
File and serve the respondent’s notice with its compliant skeleton argument. Actual late acknowledgment does not restart the period; supporting evidence and documents are subject to the permission-application restrictions.
PD 62 paragraph 12.7Does actual acknowledgment control this notice date?
No. Paragraph 12.7 uses when acknowledgment was required. Preserve the original due date and any operative court variation.
PD 62 paragraph 12.7Must the respondent include a skeleton argument?
Yes. Paragraph 12.7 requires a supporting skeleton complying with paragraph 12.2, including its specified format, length and papers-reading estimate.
PD 62 paragraph 12.2Can the respondent automatically file unrestricted evidence?
No. Paragraph 12.8 limits opposition evidence by paragraph 12.4 and requires permitted evidence to be filed and served with the notice.
PD 62 paragraph 12.8Official sources and review
Provisions used (5)
| Provision | Purpose |
|---|---|
| PD 62 paragraph 12.7 | Check the identified procedure, event, counting rule or qualification |
| PD 62 paragraph 12.2 | Check the identified procedure, event, counting rule or qualification |
| PD 62 paragraph 12.4 | Check the identified procedure, event, counting rule or qualification |
| PD 62 paragraph 12.8 | Check the identified procedure, event, counting rule or qualification |
| CPR 2.8 | Check the identified procedure, event, counting rule or qualification |