Skip to main content

England and Wales · Civil enforcement

How is an extension of the taking-control period established?

Regulation 9(3) permits a twelve-month court extension on the conditions in paragraph (4). CPR 84.5 governs the application and the actual extension’s start and recording.

5.0Rated by lawyers in California, London and Singapore“The platform is really easy to use.” — Michael B., California“The Evidence Record saved us time with our insurance on bankruptcy matters.” — Maria, London, UK“The most up-to-date service we could find.” — Li Chen, Singapore
Read why no date is calculated
Period
An actual twelve-month extension on one occasion, with its source-defined or ordered start
Trigger
Existing regulation 9 expiry, actual application and actual extension order
Rule
TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)
TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)

Official Justice UK CPR text and legislation.gov.uk statutory XML retained on October 9, 2026. The retained source metadata and acquisition receipts identify each edition. No claim of later amendments or actual local court opening is made. Taking Control of Goods text includes the May 1, 2026 changes made by SI 2026/366. Earlier notice-giving regimes require separate review.

Source guide · No automated date

Check the applicable procedure

The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period. This remains a source guide. The application, grant, actual start and prior-extension history must be known. Required service and instrument endorsement remain separate completion steps.

TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)

What lawyers say

5.0
  • “The platform is really easy to use.”

    Michael B.Employment litigation attorney · California

  • “The Evidence Record saved us time with our insurance on bankruptcy matters.”

    MariaBankruptcy and commercial attorney · London, UK

  • “The most up-to-date service we could find.”

    Li ChenArbitration practitioner · Singapore

How is an extension of the taking-control period established?

Regulation 9(3) permits a twelve-month court extension on the conditions in paragraph (4). CPR 84.5 governs the application and the actual extension’s start and recording.

Responsible actor. The enforcement agent or creditor applying for the permitted extension.

Existing regulation 9 expiry, actual application and actual extension order.

The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period.

The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period.

TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)

How does this provision count time?

  1. Where CPR 84.5(2) applies, the start is the day after existing expiry or a later day the court orders. A generic application date cannot establish the granted period.
  2. A closed court office does not prove an extension order or continuous authority to take control. Preserve the actual order and its operative start.

Where CPR 84.5(2) applies, the start is the day after existing expiry or a later day the court orders. A generic application date cannot establish the granted period.

A closed court office does not prove an extension order or continuous authority to take control. Preserve the actual order and its operative start.

TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)

Which facts prevent one automatic date?

The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period. This remains a source guide. The application, grant, actual start and prior-extension history must be known. Required service and instrument endorsement remain separate completion steps.

ResultRead the operative provision and establish the applicable branch.

The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period. Where CPR 84.5(2) applies, the start is the day after existing expiry or a later day the court orders. A generic application date cannot establish the granted period. An actual twelve-month extension on one occasion, with its source-defined or ordered start. Establish the actual applicable procedure before completing the act.

A closed court office does not prove an extension order or continuous authority to take control. Preserve the actual order and its operative start. Where CPR 84.5(2) applies, the start is the day after existing expiry or a later day the court orders. A generic application date cannot establish the granted period. No automatic computed date or purchase.

This remains a source guide. The application, grant, actual start and prior-extension history must be known. Required service and instrument endorsement remain separate completion steps. Non-TCG validity may be extended from time to time under CPR 83.3(4). The regulation 9 control-period extension has its own one-occasion limit and cannot borrow that repeat-renewal power. Check the identified alternate procedure and actual direction or events.

Which conditions and exceptions apply?

Identified actor and operative event
The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period.
Provision-specific counting and closure
Where CPR 84.5(2) applies, the start is the day after existing expiry or a later day the court orders. A generic application date cannot establish the granted period. A closed court office does not prove an extension order or continuous authority to take control. Preserve the actual order and its operative start.
Required completion and separate procedural route
This remains a source guide. The application, grant, actual start and prior-extension history must be known. Required service and instrument endorsement remain separate completion steps.
TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)
  • The extension is discretionary and limited to one occasion. The court must find the stated reasonable grounds for not taking control during the original period.
  • Non-TCG validity may be extended from time to time under CPR 83.3(4). The regulation 9 control-period extension has its own one-occasion limit and cannot borrow that repeat-renewal power.

What must the responsible actor complete?

Questions about this procedure

How is an extension of the taking-control period established?

Does applying extend the taking-control period automatically?

No. Regulation 9(3) gives the court a power to order extension, subject to paragraph (4). An application is not the grant.

TCG Regulations 2013, reg 9(3)–(4)

Can the court grant repeated twelve-month control extensions?

Paragraph (4)(b) limits this extension power to one occasion. Do not import the repeat-renewal language of the non-TCG writ rule.

TCG Regulations 2013, reg 9(4)(b); CPR 83.3(4)

What grounds must the court consider before extending the control period?

Paragraph (4)(c) requires reasonable grounds for not taking control of the debtor’s goods during the original period. The court must actually be satisfied.

TCG Regulations 2013, reg 9(4)(c)

When does an extension start after the timely application covered by CPR 84.5(2)?

It starts the day after the existing regulation 9(1) expiry, or a later day the court orders. Retain that actual later-day direction if given.

CPR 84.5(2)

Who must receive an actual control-period extension order?

CPR 84.5(3)(a) requires service on the debtor and on the creditor, enforcement agent or enforcement officer as appropriate.

CPR 84.5(3)(a)

How does the control instrument record the actual extension?

Where the specified TCG instrument is involved, CPR 84.5(3)(b) requires the court to endorse a note of the extension. Rule 83.4(6) addresses evidence of the extension.

CPR 84.5(3)(b); 83.4(6)

Official sources and review

Provisions used (15)
Provisions used in this guide
ProvisionPurpose
TCG Regulations 2013, reg 9(3)–(4); CPR 84.5(2)–(3)Check the identified procedure, event, counting rule or qualification
CPR 2.8(2)–(5)Check the identified procedure, event, counting rule or qualification
TCG Regulations 2013, regs 2, 9Check the identified procedure, event, counting rule or qualification
SI 2026/366, reg 2Check the identified procedure, event, counting rule or qualification
CPR 84.5(2)–(3)Check the identified procedure, event, counting rule or qualification
TCG Regulations 2013, reg 9(3)–(4)Check the identified procedure, event, counting rule or qualification
TCG Regulations 2013, reg 9(4)(b)Check the identified procedure, event, counting rule or qualification
CPR 83.3(4)Check the identified procedure, event, counting rule or qualification
TCG Regulations 2013, reg 9(4)(c)Check the identified procedure, event, counting rule or qualification
CPR 84.5(2)Check the identified procedure, event, counting rule or qualification
CPR 84.5(3)(a)Check the identified procedure, event, counting rule or qualification
CPR 84.5(3)(b)Check the identified procedure, event, counting rule or qualification
CPR 83.4(6)Check the identified procedure, event, counting rule or qualification
TCG Regulations 2013, reg 9(4)(b); CPR 83.3(4)Check the identified procedure, event, counting rule or qualification
CPR 84.5(3)(b); 83.4(6)Check the identified procedure, event, counting rule or qualification
Read the official controlling provision

Cookie preferences