When is a New York summary judgment motion due after note of issue?

Without a different court-set date, CPLR 3212(a) requires summary judgment within 120 days after note-of-issue filing. Issue must be joined and delay requires good cause.

5.0Rated by lawyers in California, London and Singapore“The platform is really easy to use.” — Michael B., California“The Evidence Record saved us time with our insurance on bankruptcy matters.” — Maria, London, UK“The most up-to-date service we could find.” — Li Chen, Singapore
Calculate my deadline
Period
120 calendar days
Trigger
Actual filing of the note of issue, where the court has set no different motion date
Rule
CPLR 3212(a)
CPLR 3212(a)

Current official section, website revision from 2022-05-13, reviewed. The revision label is not an inferred effective date.

Free calculator · No account needed

Calculate your deadline

Loading calculator…

What lawyers say

5.0
  • “The platform is really easy to use.”

    Michael B.Employment litigation attorney · California

  • “The Evidence Record saved us time with our insurance on bankruptcy matters.”

    MariaBankruptcy and commercial attorney · London, UK

  • “The most up-to-date service we could find.”

    Li ChenArbitration practitioner · Singapore

Which event starts the CPLR 3212(a) period?

Preserve the actual note-of-issue filing and confirm that issue has been joined. Service of the note, trial assignment and discovery completion are different events.

Read the scheduling and part orders. The statutory 120-day branch applies only if the court has not set a different date.

Responsible actor. The party moving for summary judgment after issue has been joined. The 120-day CPLR 3212(a) default after established note-of-issue filing and issue joined. No different court-set date, granted late-motion leave or separate CPLR 3213 procedure.

CPLR 3212(a)

How is this service or filing period counted?

  1. Preserve the actual note-of-issue filing and confirm that issue has been joined. Service of the note, trial assignment and discovery completion are different events.
  2. Read the scheduling and part orders. The statutory 120-day branch applies only if the court has not set a different date.
  3. Exclude the established trigger day and count 120 calendar days forward. Intermediate weekends and public holidays remain in the count. General Construction Law 25-a permits the next succeeding business day for a closed final statutory day.
  4. Make the noticed motion through service under CPLR 2211, and complete separate required filing and court furnishing. Preparing or filing papers alone does not prove timely making of the noticed motion.

General Construction Law 20 excludes the event day. Its closed-intervening-day exception applies to an exact two-day period, not to a one-day period. Intermediate weekends and public holidays count in other calendar-day periods. Section 25-a expressly includes statutory periods before which an act is due and permits the next succeeding business day for a closed final day. Rollover can place a backward boundary on the return date; preserve the stated hour and actual court directions. Roberts, a separately identified uncorrected Supreme Court decision concerning opposition to a cross-motion, applied section 25-a to a Sunday boundary before a Monday return. It is corroboration of that final-day treatment, not a different universal briefing rule.

The independently derived 2026 and 2027 calendar follows General Construction Law 24 and Election Law 8-100. It includes Lincoln’s Birthday, Flag Day on the second Sunday in June, Juneteenth, general election day and the other specified holidays. Section 24 adds the next day when a listed holiday falls on Sunday, except Flag Day. A Saturday holiday is not automatically observed on Friday under this provision. Additional appointed holidays and actual court or system closures require separate proof.

These calculators cover established events and final dates within January 1, 2026 through December 31, 2027. They require the disclosed statutory branch, independently valid service, no unsupported method addition, no different actual court order and no additional closure. Backward presets require an actual open-day return date. Earlier editions, the 2020 executive-order toll and dates beyond the retained calendar require separate review and receive no computed or paid date. This software coverage boundary does not establish that an actual act is late.

General Construction Law 20, calendar days and exact two-day exception

What does the independently derived example establish?

Fictitious example

The 120-day CPLR 3212(a) default after established note-of-issue filing and issue joined. No different court-set date, granted late-motion leave or separate CPLR 3213 procedure. Fictitious established event on the input date. The 120-day CPLR 3212(a) default after established note-of-issue filing and issue joined. No different court-set date, granted late-motion leave or separate CPLR 3213 procedure.

Example counting steps
StepWhat is countedDate
Established procedural eventActual filing of the note of issue, where the court has set no different motion dateSeptember 1, 2026
Disclosed statutory component120 calendar daysWednesday, December 30, 2026
Example resultWednesday, December 30, 2026

Fictitious established facts. The result does not prove valid service, the required exception, actual filing, preserved jurisdiction or a granted court extension. The applicable hour and actual court directions remain separate checks.

Try these dates in the calculator

Which facts change this procedural requirement?

Court-set date
The court may set a different cutoff no earlier than thirty days after note-of-issue filing. An actual applicable order replaces this selected default.
Good cause for delay
Brill requires a satisfactory explanation for the delay itself. Merits and lack of prejudice alone do not supply good cause for an untimely motion.
Motion made by service
CPLR 2211 makes a noticed motion when its notice of motion or order to show cause is served. Preserve the actual service event.
Consumer-credit additional notice
Section 3212(j) contains an additional clerk-mailed notice procedure where an unrepresented consumer defendant is involved. Its fourteen- or nineteen-day return-date requirements do not replace the note-of-issue clock.
Issue joined and separate procedure
Subdivision (a) requires issue joined. Summary judgment in lieu of complaint under CPLR 3213 is a different procedure and does not use this default.
Edition and calendar coverage
These calculators cover established events and final dates within January 1, 2026 through December 31, 2027. They require the disclosed statutory branch, independently valid service, no unsupported method addition, no different actual court order and no additional closure. Backward presets require an actual open-day return date. Earlier editions, the 2020 executive-order toll and dates beyond the retained calendar require separate review and receive no computed or paid date. This software coverage boundary does not establish that an actual act is late.
CPLR 3212(a)
  • The 120-day CPLR 3212(a) default after established note-of-issue filing and issue joined. No different court-set date, granted late-motion leave or separate CPLR 3213 procedure.
  • The selected date supplies only the disclosed statutory branch. It does not validate the facts or authorize an unmodeled alternative.

Which documents, completed acts and proof should be retained?

Questions about CPLR 3212(a)

When is a New York summary judgment motion due after note of issue?

Do I count from service or filing of the note of issue?

Filing. CPLR 3212(a) identifies the note-of-issue filing event for this selected 120-day default.

CPLR 3212(a)

Can a strong motion be late merely because the opponent suffers no prejudice?

Brill rejects merits and no prejudice alone as good cause. Establish a satisfactory explanation for the actual delay.

Brill v City of New York, 2 NY3d 648 (2004)

Does the calculator override a shorter court cutoff?

No. Establish the actual order first. The default applies only when no different date has been set.

CPLR 3212(a)

Official New York procedural, counting and filing sources

Provisions used (11)
Provisions used in this guide
ProvisionPurpose
CPLR 3212(a)The particular actor, event, period and required act
Brill v City of New York, 2 NY3d 648 (2004)The individually identified statutory, judicial, counting, service or filing qualification
CPLR 2211The individually identified statutory, judicial, counting, service or filing qualification
General Construction Law 20, calendar days and exact two-day exceptionThe individually identified statutory, judicial, counting, service or filing qualification
General Construction Law 24, public holidaysThe individually identified statutory, judicial, counting, service or filing qualification
General Construction Law 25-a, next succeeding business dayThe individually identified statutory, judicial, counting, service or filing qualification
Election Law 8-100(1)(c), general election dayThe individually identified statutory, judicial, counting, service or filing qualification
CPLR 2103, valid service and specified response additionsThe individually identified statutory, judicial, counting, service or filing qualification
CPLR 2211, when a noticed motion is madeThe individually identified statutory, judicial, counting, service or filing qualification
22 NYCRR 202.5-b(d), (f), (h), (i)The individually identified statutory, judicial, counting, service or filing qualification
Roberts v New York City Police Dept., 2022 NY Slip Op 33761(U), at 4Identified trial-court application of statutory closed final-day treatment; not a universal briefing order
Read the official provision

Cookie preferences

Deadline Engine uses necessary cookies for authentication and security. You can choose whether we may load Plausible Analytics to measure aggregate site use. We do not use advertising or marketing tracking. You can change this any time from the footer. Read the Cookie Policy.