United States · New York limitation periods
How is New York mortgage-action timing established?
CPLR 213(4) states six years for its mortgage instruments. Accrual, anti-reset rules and mortgage-specific recommencement require separate document review.
- Period
- 6 years with separate instrument accrual and section 205-a conditions
- Trigger
- Established instrument accrual, acceleration history and applicable termination
- Rule
- CPLR 213(4)(a)–(b)
Current official statutory text reviewed. A displayed Senate revision date is not an amendment effective date.
Source guide · No automated date
How is New York mortgage-action timing established?
The single date preset cannot establish instrument accrual, acceleration estoppel, anti-reset requirements or mortgage-specific refiling conditions.
CPLR 213(4)(a)–(b)What lawyers say
5.0“The platform is really easy to use.”
Michael B.Employment litigation attorney · California
“The Evidence Record saved us time with our insurance on bankruptcy matters.”
MariaBankruptcy and commercial attorney · London, UK
“The most up-to-date service we could find.”
Li ChenArbitration practitioner · Singapore
Which event controls this CPLR 213(4)(a)–(b) inquiry?
Identify the instrument described in section 213(4) and establish the actual accrued claim, acceleration history and prior judicial determinations.
Paragraph (4)(a) and (b) contain stated acceleration estoppel rules with an expressed-judicial-determination exception based on a timely defense.
Section 203(h) prohibits the described unilateral waiver, postponement, cancellation, toll, revival or reset after accrual unless expressly prescribed by statute.
Section 205-a supplies a narrower mortgage recommencement regime. General section 205(c) excludes proceedings governed by that provision.
CPLR 213(4)(a)–(b)Which periods must be established before counting?
- Identify the instrument described in section 213(4) and establish the actual accrued claim, acceleration history and prior judicial determinations.
- Paragraph (4)(a) and (b) contain stated acceleration estoppel rules with an expressed-judicial-determination exception based on a timely defense.
- Section 203(h) prohibits the described unilateral waiver, postponement, cancellation, toll, revival or reset after accrual unless expressly prescribed by statute.
- Section 205-a supplies a narrower mortgage recommencement regime. General section 205(c) excludes proceedings governed by that provision.
- This guide supplies no fixed date. Establish the applicable statutory branches and their actual events before applying any calendar-month, calendar-year or final-day provision.
- Preserve the instrument, acceleration, prior judicial determinations and any qualifying termination. Section 205-a requires its own recommencement and service proof.
A calendar anniversary cannot decide the statutory classification or supply missing facts. No computed or paid date is published.
CPLR 213(4)(a)–(b)What distinguishes the relevant statutory branches?
Fictitious comparison. Two lenders select the same alleged acceleration date. Only one has the express judicial invalid-acceleration determination described in the statute. A common six-year anniversary cannot resolve both histories.
The single date preset cannot establish instrument accrual, acceleration estoppel, anti-reset requirements or mortgage-specific refiling conditions.
Which qualifications change this inquiry?
- Acceleration determination
- Preserve prior proceedings and any expressed judicial determination that acceleration was invalid on the stated timely defense.
- No unilateral reset
- Do not treat a lender’s later unilateral act as automatically creating new accrual under section 203(h).
- Mortgage recommencement
- Section 205-a lists additional neglect exclusions, plaintiff or assignee conditions, both commencement and service, and its single six-month extension ceiling.
- Historical executive-order toll
- The calculators accept selected events after November 3, 2020. They do not apply the 2020 executive-order toll. Brash distinguishes a toll from a suspension. Historical events require separate review and receive no calculated or paid date here. Do not add 228 days to every historical event without testing its actual applicability.
- Preserve the applicable edition and establish the actual statutory facts independently.
- The single date preset cannot establish instrument accrual, acceleration estoppel, anti-reset requirements or mortgage-specific refiling conditions.
Which facts and completed acts should be preserved?
Questions about CPLR 213(4)(a)–(b)
How is New York mortgage-action timing established?
Does voluntary discontinuance automatically restart six years?
No. Section 203(h) bars the described unilateral reset unless expressly prescribed by statute.
CPLR 203Is every mortgage recommencement allowed under general section 205?
No. Section 205(c) excludes the separate section 205-a regime.
CPLR 205Does the six-year text identify my accrual date?
No. The actual instrument and acceleration history need their own legal and factual determination.
CPLR 213Official New York sources and review
Provisions used (13)
| Provision | Purpose |
|---|---|
| CPLR 213(4)(a)–(b) | The particular statutory procedure and its conditions |
| CPLR 203(a), (c) | The separately identified qualification or accrual provision |
| CPLR 205-A | The separately identified qualification or accrual provision |
| CPLR 205 | The separately identified qualification or accrual provision |
| CPLR 202 | The separately identified qualification or accrual provision |
| Brash v Richards, 195 AD3d 582 (2d Dept 2021) | Historical tolling and the calculator’s scope boundary |
| General Construction Law 20 | Applicable event-day, calendar-interval or statutory final-day provision |
| General Construction Law 30 | Applicable event-day, calendar-interval or statutory final-day provision |
| General Construction Law 58 | Applicable event-day, calendar-interval or statutory final-day provision |
| General Construction Law 24 | Applicable event-day, calendar-interval or statutory final-day provision |
| General Construction Law 25-a | Applicable event-day, calendar-interval or statutory final-day provision |
| CPLR 304 | Commencement by filing, separate from defendant service |
| 22 NYCRR 202.5-b(d)(3)(i), (f)(1) | Recorded transmission and required fee information in the applicable NYSCEF program; initiating filing does not itself serve a defendant |